Construction Update – April 2020

The vertical construction in Tower Q1 Level 07 is complete and works have commenced on the concrete slab over Level 07. The concrete slabs in Towers Q2 and Q3 over Level 06 are ready and works on vertical construction at Level 07 in both towers are ongoing. Vertical construction in Tower Q4 Level 08 is now ready, and final preparations are underway for the casting of the concrete slab over Level 08.

The installation of the mechanical and electrical services are continuing at all Basement Levels including the tower cores. The installation of rainwater and sewer systems and plastering works of the tower cores at basement levels is also in progress