Construction Update – February 2018

Excavation, piling and shoring.

The bulk excavation works for the site are presently at 95% completion. Over the past month, piling works have been completed, with the remaining shotcrete and rock bolting works currently in progress.

Detailed excavation works are ongoing with the raft foundation for Tower Q3 now complete and the raft foundations for Towers Q1 and Q2 presently in progress.

Construction Works

Tower Q3 foundation has an approximate area of 1,030m². Construction works on the foundations of Tower Q3 are ongoing.

  • Blinding, membrane, geotextile and protective concrete screed works have been completed.
  • All lightning protection rods required for this tower’s foundations have been installed.
  • The installation of the reinforcement steel required for this foundation has started, A total of 260 tonnes of reinforcement steel is expected to be used.

More developments held in March 2018.