Construction Update – February 2020

Vertical construction works on Level 07 of Tower Q4 are ongoing. The concrete slab over Level 05 of Tower Q1 is now ready and works are ongoing on the vertical construction of Level 06. The vertical construction over Level 05 in both Tower Q2 and Tower Q3 are almost complete. Preparation works for the concrete slab at Level 05 in both these towers have also started.

The installation of the mechanical and electrical services are continuing at all Basement Levels including within the tower cores. The installation of rainwater and sewer systems has started while plastering works of the tower cores at basement levels is also in progress.