Construction Update - May 2022 - the quad

Construction Update – May 2022

The floor-to-ceiling and curtain-wall fa├žade in all of the lower floors in Tower Q4 are in progress.

The installation of stainless-steel railings in the maintenance balconies & bridges are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The steel bridges connecting the Towers Q1 & Q2 are currently being installed with raised flooring. The aluminium composite cladding material works are ongoing.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the Tower cores of Q2. The infrastructure works in Tower Q2 are ongoing.

Level 10 of Q3 has been handed over. Level 01 of Tower Q3 is in operation. Levels 01, 02, 06, 07, 08 and 09 of Tower Q3 are in operation.

All planters in Level 00 are going through planting and irrigation works. The public green wall in adjacent with the public lifts in Tower Q2 on Levels 00 & 01 have been completed. Testing of external lights are ongoing. The Piazza flooring in Level 01 is completed.

The car parking system is now in operation. Levels B01 & B02 are in operation.

Take a look at our May 2022 Update Video here.