Construction Update – October 2020

October was another month of busy activity on The Quad site. Construction works continued on schedule with Level 12 of Tower Q1, Level 10 of Tower Q2, Levels 13 & 14 of Tower Q3 and Level 14 of Tower Q4, all having been roofed over. Vertical construction works on the overlying floors is ongoing.

The installation of the mechanical and electrical services is continuing at all Basement Levels including the tower cores. Plastering and Marble works of the tower cores at all basement levels as well as within Tower Q3 are also in progress. The installation of rainwater and sewer system is continuing, and the floor-to-ceiling fa├žade is being installed in all the lower floors of the towers.

Generators set in placeInstallation of the two steel bridges linking Tower Q2 to Tower Q3 has been completed. The installation of the first bridge linking Tower Q3 to Tower Q4 is in progress whilst the next two bridges being manufactured.

The transformers and the generators serving The Quad Business Towers have been received and have been lowered into place within the sub-station and the generators room.

Interested in learning more about office space relocation opportunities to The Quad Business Towers? Reach out to one of our representatives here.