Construction Update – October 2022

The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 are in progress.

The fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 and Q4 with liner, railing works. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The works on the steel bridges connecting the towers are ongoing. The aluminium composite cladding material works, the raised flooring and the railing of metal mass.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores and roof top of Tower Q2.

Levels 01, 02, 05, 06, 07, 08, 09 and 10 of Tower Q3 are in operation.

Works in Levels 03 and 16 of Tower Q3 are ongoing.

The infrastructure works of Tower Q2 are ongoing, while works on Level 01 are closing completion & works on Level 07 have commenced.

Car parking Levels -1 and -2 are in operation.

Piazza works are complete on Levels 00 and 01 subject to minor works to be carried out.

Landscaping works are ongoing on Level 01 behind Tower Q4.

Take a look at our October 2022 Update Video here.