Construction Update – March 2022

The Quad's Construction Update - March 2022

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – February 2022

The Quad's Construction Update - February 2022

The roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade works in all of the lower floors in Tower Q4 are in progress. Fixing of stainless-steel railing in […]

The Quad Central welcomes first tenants as operations begin.

The Quad Central welcomes first tenants as operations begin.

The Quad Central is now operational, as Apex Group, the first tenant to have signed on, moves into its new premises. Boasting an outstanding, central business address, the mixed-use development is being touted as the ‘future of workspace’ which will include professional and commercial office spaces, as well as retail and amenity outlets. “It is […]

Construction Update – January 2022

The Quad's Construction Update - January 2022

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance […]

Construction Update – December 2021

The Quad centre's Construction Update - December 2021

The roofing works on Tower Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 are in progress. The fixing of stainless-steel railing […]

Construction Update – October 2021

Indoor view of Quad's office

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]

Greens Supermarket to Expand Operations to the Quad Central.

The Quad Central and Greens Supermarket are excited to announce that Greens will open a Supermarket and a Bistro at the Quad Central, within the Central Business District, Mriehel: A fully-fledged supermarket consisting of 2,900 square meters, opening onto the 7,000 square meter landscaped pedestrianized Piazza. The size of the area has allowed the supermarket […]

Construction Update – August 2021

Vertical construction works in Tower Q4 on Level 20 are completed. Roofing works on Towers Q4 are ongoing. Tower Crane beside Tower Q1 has been disassembled and the voids have been roofed off to L00. The closure of the voids of the tower crane beside Tower Q2 have been completed. The installation of the mechanical […]

Construction Update – July 2021

The roofing works on Towers Q1 are now complete. Roofing works on Tower Q4 are ongoing. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are ongoing. The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of […]