Brown’s joins The Quad Central tenant line-up 

Brown’s joins The Quad Central tenant line-up

Brown’s Pharma Limited is the largest retail pharmacy Group in Malta Established in 1998 by Alexander Fenech and Robert Spiteri, pharmacists, long-time friends, and business partners. Brown’s has grown steadily over the past 24 years and has now opened doors to its 24th pharmacy at The Quad Central.  The new pharmacy joins the increasingly growing […]

Construction Update – June 2022

Construction Update in June 2022 - the Quad

Piazza Level 00 has now opened to the public, with three outlets now operational. The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of […]

Construction Update – March 2022

Construction Update - March 2022 - the quad centre

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – September 2021

Construction Update - September 2021 - The Quad Business Towers

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The floor-to-ceiling and curtain-wall façade in all the lower floors of the towers Q1, Q2 and Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and […]

Construction Update – August 2021

Construction Update - August 2021 - The Quad Business Towers

Vertical construction works in Tower Q4 on Level 20 are completed. Roofing works on Towers Q4 are ongoing. Tower Crane beside Tower Q1 has been disassembled and the voids have been roofed off to L00. The closure of the voids of the tower crane beside Tower Q2 have been completed. The installation of the mechanical […]

Construction Update – June 2021

Construction Update - June 2021 ,The Quad Business Towers

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress. The installation of the mechanical and electrical services are in progress at all Basement Levels including the […]