Construction Update – June 2022

Outer space of the quad office in Malta for rent and sale

Piazza Level 00 has now opened to the public, with three outlets now operational. The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of […]

Construction Update – May 2022

The Quad's Construction Update - May 2022

The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 are in progress. The installation of stainless-steel railings in the maintenance balconies & bridges are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of these balconies are also being covered with aluminium composite white […]

Fort Fitness signs on as new Fitness & Wellness tenant

Fort Fitness is the new Fitness & Wellness tenant of the Quad centre

The Quad Central recently announced the addition of Fort Fitness, one of the island’s largest fitness facilities, as its newest tenant. This high-end fitness centre, fasting establishing itself as the leading force for fitness, is slated to open its doors later on this year. This latest partnership consolidates The Quad’s strategy for future growth and […]

Construction Update – March 2022

The Quad's Construction Update - March 2022

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

The Quad Central welcomes first tenants as operations begin.

The Quad Central welcomes first tenants as operations begin.

The Quad Central is now operational, as Apex Group, the first tenant to have signed on, moves into its new premises. Boasting an outstanding, central business address, the mixed-use development is being touted as the ‘future of workspace’ which will include professional and commercial office spaces, as well as retail and amenity outlets. “It is […]

Construction Update – October 2021

Indoor view of Quad's office

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]

Construction Update – September 2021

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The floor-to-ceiling and curtain-wall façade in all the lower floors of the towers Q1, Q2 and Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and […]

Dr Juice confirms key outlet for the Quad Central

Dr. Juice, one of Malta’s best loved local brands has confirmed its plans to open an outlet at the Quad Central by the end of 2021, offering smoothies, juices, and healthy food. This move promises to bring a health-first experience, supported by a sustainable approach, to Malta’s Central Business District (CBD) – the hub of […]

Construction Update – August 2021

Vertical construction works in Tower Q4 on Level 20 are completed. Roofing works on Towers Q4 are ongoing. Tower Crane beside Tower Q1 has been disassembled and the voids have been roofed off to L00. The closure of the voids of the tower crane beside Tower Q2 have been completed. The installation of the mechanical […]

Construction Update – July 2021

The roofing works on Towers Q1 are now complete. Roofing works on Tower Q4 are ongoing. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are ongoing. The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of […]