Construction Update – October 2022

The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 are in progress. The fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 and Q4 with liner, railing works. The sides and underside of these balconies are also being covered with aluminium composite white cladding material. The works […]

Construction Update – August 2022

The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. The fixing of stainless-steel railing in the maintenance balconies are ongoing in Tower Q4 with liner & railing works taking place. The sides and underside of these balconies are also being covered with aluminium composite white cladding material. […]

Brown’s joins The Quad Central tenant line-up 

Brown’s joins The Quad Central tenant line-up

Brown’s Pharma Limited is the largest retail pharmacy Group in Malta Established in 1998 by Alexander Fenech and Robert Spiteri, pharmacists, long-time friends, and business partners. Brown’s has grown steadily over the past 24 years and has now opened doors to its 24th pharmacy at The Quad Central.  The new pharmacy joins the increasingly growing […]

Construction Update – July 2022

Construction Update - July 2022- the quad

The floor-to-ceiling and curtain-wall façade in all of the lower floors Tower Q4 is in progress. The fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works also progressing. The sides and underside of these balconies are also being covered with aluminium composite white cladding […]

Construction Update – June 2022

Construction Update in June 2022 - the Quad

Piazza Level 00 has now opened to the public, with three outlets now operational. The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of […]

Construction Update – May 2022

Construction Update - May 2022 - the quad

The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 are in progress. The installation of stainless-steel railings in the maintenance balconies & bridges are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of these balconies are also being covered with aluminium composite white […]

Fort Fitness signs on as new Fitness & Wellness tenant

Fort Fitness signs on as new Fitness & Wellness tenant

The Quad Central recently announced the addition of Fort Fitness, one of the island’s largest fitness facilities, as its newest tenant. This high-end fitness centre, fasting establishing itself as the leading force for fitness, is slated to open its doors later on this year. This latest partnership consolidates The Quad’s strategy for future growth and […]

Construction Update – March 2022

Construction Update - March 2022 - the quad centre

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

The Quad Central welcomes first tenants as operations begin.

The Quad Central welcomes first tenants as operations begin.

The Quad Central is now operational, as Apex Group, the first tenant to have signed on, moves into its new premises. Boasting an outstanding, central business address, the mixed-use development is being touted as the ‘future of workspace’ which will include professional and commercial office spaces, as well as retail and amenity outlets. “It is […]

Construction Update – October 2021

Construction Update - October 2021 - the Quad

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]