Construction Update – April 2022

The Quad's Construction Update - April 2022

The installation of VRF units at roof level of Tower Q3 is now completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all the lower floors of the Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1 […]

Construction Update – March 2022

The Quad's Construction Update - March 2022

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – October 2021

Indoor view of Quad's office

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]

Construction Update – September 2021

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The floor-to-ceiling and curtain-wall façade in all the lower floors of the towers Q1, Q2 and Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and […]

Construction Update – July 2021

The roofing works on Towers Q1 are now complete. Roofing works on Tower Q4 are ongoing. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are ongoing. The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of […]

Construction Update – June 2021

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress. The installation of the mechanical and electrical services are in progress at all Basement Levels including the […]

Construction Update – May 2021

Roofing works on Towers Q1 and Q2 are ongoing. Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all 4 towers are now complete. The installation of the mechanical and electrical services […]

Construction Update – April 2021

Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all the four towers are now complete. Roofing works on Towers Q1 and Q2 are ongoing. The installation of the mechanical & electrical […]

Construction Update – March 2021

Construction works at roof level on Towers Q1 and Q2 are ongoing whilst Construction works of Tower Q3 are complete. The concrete slab in Tower Q4 Level 18 is also complete and vertical construction works on Level 19 are ongoing. The installation of the mechanical and electrical services is progressing well at all Basement Levels […]

Construction Update – February 2021

Construction works of the concrete slab in Tower Q1 over Level 15 is complete and the roofing works on Level 16 are progressing. The concrete slab in Tower Q2 above L13 are also complete and roofing works at Level 14 are ongoing. Construction works of Tower Q3 are complete. The vertical construction and concrete slab […]