Construction Update – June 2022

Construction Update in June 2022 - the Quad

Piazza Level 00 has now opened to the public, with three outlets now operational. The floor-to-ceiling and curtain-wall façade in all the lower floors of Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of […]

Construction Update – March 2022

Construction Update - March 2022 - the quad centre

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – June 2021

Construction Update - June 2021 ,The Quad Business Towers

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress. The installation of the mechanical and electrical services are in progress at all Basement Levels including the […]

Construction Update – May 2021

Construction Update - May 2021 - The Quad centre

Roofing works on Towers Q1 and Q2 are ongoing. Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all 4 towers are now complete. The installation of the mechanical and electrical services […]