Construction Update – August 2022

The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. The fixing of stainless-steel railing in the maintenance balconies are ongoing in Tower Q4 with liner & railing works taking place. The sides and underside of these balconies are also being covered with aluminium composite white cladding material. […]

Construction Update – December 2021

Construction Update - December 2021 - the quad centre

The roofing works on Tower Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 are in progress. The fixing of stainless-steel railing […]