Construction Update – March 2022

Construction Update - March 2022 - the quad centre

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – February 2022

Construction Update - February 2022 - the Quad

The roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade works in all of the lower floors in Tower Q4 are in progress. Fixing of stainless-steel railing in […]

The Quad Central welcomes first tenants as operations begin.

The Quad Central welcomes first tenants as operations begin.

The Quad Central is now operational, as Apex Group, the first tenant to have signed on, moves into its new premises. Boasting an outstanding, central business address, the mixed-use development is being touted as the ‘future of workspace’ which will include professional and commercial office spaces, as well as retail and amenity outlets. “It is […]

Construction Update – January 2022

Construction Update - January 2022 - the quad centre

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance […]

Construction Update – December 2021

Construction Update - December 2021 - the quad centre

The roofing works on Tower Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 are in progress. The fixing of stainless-steel railing […]

Construction Update – November 2021

Construction Update - November 2021

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The works to enclose the tower crane holes of Tower Q2 have been closed and completed. The floor-to-ceiling and curtain-wall façade in all of the […]

Construction Update – October 2021

Construction Update - October 2021 - the Quad

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]

Greens Supermarket to Expand Operations to the Quad Central.

Greens Supermarket to Expand Operations to the Quad Central.

The Quad Central and Greens Supermarket are excited to announce that Greens will open a Supermarket and a Bistro at the Quad Central, within the Central Business District, Mriehel: A fully-fledged supermarket consisting of 2,900 square meters, opening onto the 7,000 square meter landscaped pedestrianized Piazza. The size of the area has allowed the supermarket […]

Dr Juice confirms key outlet for the Quad Central

Dr Juice confirms key outlet for the Quad Central

Dr. Juice, one of Malta’s best loved local brands has confirmed its plans to open an outlet at the Quad Central by the end of 2021, offering smoothies, juices, and healthy food. This move promises to bring a health-first experience, supported by a sustainable approach, to Malta’s Central Business District (CBD) – the hub of […]

Construction Update – August 2021

Construction Update - August 2021 - The Quad Business Towers

Vertical construction works in Tower Q4 on Level 20 are completed. Roofing works on Towers Q4 are ongoing. Tower Crane beside Tower Q1 has been disassembled and the voids have been roofed off to L00. The closure of the voids of the tower crane beside Tower Q2 have been completed. The installation of the mechanical […]