Construction Update – June 2021

Construction Update - June 2021 ,The Quad Business Towers

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress. The installation of the mechanical and electrical services are in progress at all Basement Levels including the […]

Construction Update – May 2021

Construction Update - May 2021 - The Quad centre

Roofing works on Towers Q1 and Q2 are ongoing. Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all 4 towers are now complete. The installation of the mechanical and electrical services […]

Construction Update – April 2021

Construction Update - April 2021- The Quad Business Towers

Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all the four towers are now complete. Roofing works on Towers Q1 and Q2 are ongoing. The installation of the mechanical & electrical […]

Construction Update – March 2021

Construction works at roof level on Towers Q1 and Q2 are ongoing whilst Construction works of Tower Q3 are complete. The concrete slab in Tower Q4 Level 18 is also complete and vertical construction works on Level 19 are ongoing. The installation of the mechanical and electrical services is progressing well at all Basement Levels […]

Construction Update – February 2021

A building under construction that represents one of the Quad's Projects

Construction works of the concrete slab in Tower Q1 over Level 15 is complete and the roofing works on Level 16 are progressing. The concrete slab in Tower Q2 above L13 are also complete and roofing works at Level 14 are ongoing. Construction works of Tower Q3 are complete. The vertical construction and concrete slab […]