Construction Update – May 2022

The Quad's Construction Update - May 2022

The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 are in progress. The installation of stainless-steel railings in the maintenance balconies & bridges are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of these balconies are also being covered with aluminium composite white […]

Construction Update – March 2022

The Quad's Construction Update - March 2022

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress. Fixing of stainless-steel […]

Construction Update – February 2022

The Quad's Construction Update - February 2022

The roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade works in all of the lower floors in Tower Q4 are in progress. Fixing of stainless-steel railing in […]

Construction Update – January 2022

The Quad's Construction Update - January 2022

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 is in progress. Fixing of stainless-steel railing in the maintenance […]

Construction Update – December 2021

The Quad centre's Construction Update - December 2021

The roofing works on Tower Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. The fixing of stainless-steel railing in Tower Q2 roof is in progress. The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 are in progress. The fixing of stainless-steel railing […]

Construction Update – October 2021

Indoor view of Quad's office

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced. The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced. The floor-to-ceiling and curtain-wall façade in all […]

Greens Supermarket to Expand Operations to the Quad Central.

The Quad Central and Greens Supermarket are excited to announce that Greens will open a Supermarket and a Bistro at the Quad Central, within the Central Business District, Mriehel: A fully-fledged supermarket consisting of 2,900 square meters, opening onto the 7,000 square meter landscaped pedestrianized Piazza. The size of the area has allowed the supermarket […]

Construction Update – July 2021

The roofing works on Towers Q1 are now complete. Roofing works on Tower Q4 are ongoing. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are ongoing. The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of […]

Construction Update – June 2021

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress. The installation of the mechanical and electrical services are in progress at all Basement Levels including the […]

Construction Update – May 2021

Roofing works on Towers Q1 and Q2 are ongoing. Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all 4 towers are now complete. The installation of the mechanical and electrical services […]