Construction Update – April 2022

The installation of VRF units at roof level of Tower Q3 is now completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress.

The floor-to-ceiling and curtain-wall façade in all the lower floors of the Tower Q4 is in progress.

Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1 & Q2. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores of Q2. The infrastructure works in Tower Q2 have commenced.

Levels 01 & 05 in Tower Q3 have been handed over to their respective tenants. Level 01 is in operation. Works in Level 10 are ongoing. Apart from Level 01, Levels 02, 06, 07, 08 and 09 of Tower Q3 are in operation.

The steel bridges connecting Towers Q1 & Q2 are now being finished with raised flooring. The steel bridges connecting the Towers Q2 to Q3 and Q3 to Q4 are currently being covered with aluminium composite cladding material.

All planters in Piazza Level 00 are currently going on with planting and irrigation works.  Testing of external lights at Piazza levels ongoing.

Car parking system is now in operation at levels B01 & B02.

Take a look at our April 2022 Update Video here.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email