Construction Update – August 2019

During August, the remaining slab over Level 00, beneath Towers Q2 and Q3, has been completed. Proprietary void-formers have been introduced into the concrete slab to reduce its self-weight and enhance the strength of the concrete. Vertical construction works on columns and walls at Level 01 are currently ongoing, whilst work on the slab over Level 01 (beneath Tower Q1) has started. Preparatory works for the re-location and installation of The Quad Site Project Management Offices and contractors’ offices are in progress.