Construction Update – August 2020

The concrete slab over Level 10 of Tower Q1 is complete with vertical construction works at Level 11 ongoing. Works on the concrete slab over Level 09 of Tower Q2 are ongoing, whereas vertical construction and the concrete slabs over Level 11 of Tower Q3 and Level 12 of Tower Q4 have been completed during August.

The installation of the mechanical and electrical services is continuing at all basement levels including the tower cores. The installation of the rainwater and sewer systems as well as the plastering works of the tower cores at basement levels are also in progress.

The floor-to-ceiling fa├žade has been installed in Tower Q4 Levels 02 and 03 and in Tower Q3 Levels 03 and 04, with the glazing of the facades in progress.

The installation of the first steel bridge linking Towers Q2 and Q3 has been completed.

Interested in learning more about office space relocation opportunities to The Quad Business Towers? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email