Vertical construction works in Tower Q4 on Level 20 are completed. Roofing works on Towers Q4 are ongoing. Tower Crane beside Tower Q1 has been disassembled and the voids have been roofed off to L00. The closure of the voids of the tower crane beside Tower Q2 have been completed.
The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of VRF units at roof level of Tower Q3 is in progress. Installation of rainwater and sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 are also in progress. Finishing works in the reception area of Tower Q3 Level 01 are nearing completion. Installation of internal staircase railings in Tower Q3 are ongoing. Tower Q3 Lift lobby tiling works are ongoing. Completed works of enclosure reception area. Fit out works of Levels 6 and 7 are completed and the commissioning has started, the tenant’s furniture has been installed.
The floor-to-ceiling and curtain-wall façade are being installed in all the lower floors of towers Q1, Q2 and Q4 respectively. The fixing of the stainless-steel railing on the balconies are ongoing in Towers Q1, Q2 and Q3. The sides and underside of these balconies are also being covered with aluminium composite cladding material.
The steel bridges connecting the towers Q1 and Q2 at level 2 will be covered with aluminium composite cladding material are ongoing.
The granite tiling of the Piazza is now in advanced stages. Waterproofing and works on planters in the Piazza are on going.