Construction Update – December 2019

The concrete slabs over Level 03 of Towers Q2 and Q3 are in progress. Vertical construction works on Level 04 of Tower Q1 is also in progress and nearing completion. The concrete slab over Tower Q4 Level 04 is 50% ready and works are ongoing on the remaining part. The installation of the mechanical and electrical services at Basement Levels are ongoing. Preparatory works for the installation of rainwater and sewer systems have also continued.