Construction Update – December 2020

Construction works at The Quad continued throughout December. Works on the concrete slab over Level 14 of Tower Q1 are in progress, whilst works on the concrete slab over Level 12 of Tower Q2 are now complete. The concrete slab and vertical construction in Tower Q3 over L16 are complete with vertical construction at last Level 17 in progress. The vertical construction and concrete slab in Tower Q4 Level 16 are complete.

The installation of the mechanical and electrical services are continuing at all Basement Levels including the tower cores. The installation of rainwater and sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 is also in progress. Staircase granite works are complete at basement levels whilst it is in progress on Tower Q3,

The floor-to-ceiling and curtain-wall façade is being installed in all the lower floors of the towers.

The two steel bridges linking Tower Q2 to Tower Q3 and one of the two steel bridge linking Tower Q3 to Tower Q4 have been installed. One of the three bridges linking Tower Q1 to Tower Q2 is also installed. The manufacturing of the other five bridges is in progress..

Interested in learning more about office space relocation opportunities to The Quad Business Towers? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email