Construction Update – February 2022

The roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress.

The floor-to-ceiling and curtain-wall façade works in all of the lower floors in Tower Q4 are in progress.

Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and Q3. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Security room in Level 00 is now completed and operational. The parking system has been commissioned.

The steel bridges connecting Towers Q1 and Q2 are now completely finished. The steel bridges connecting Towers Q2 & Q3 and Q3 & Q4 have started to be covered with aluminium composite cladding material.

Waterproofing and granite tiling works in Zone 3 are completed. Landscaping works in front of Q2 L00 is completed. Filling of planters in the piazza at Level 00 with graded sub-base. 

Take a look at our February 2022 Update Video here.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email