Construction Update – January 2022

Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof is in progress.

The floor-to-ceiling and curtain-wall façade in all of the lower floors in Tower Q4 is in progress.

Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and Q3. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. The installation of rainwater and sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 is also in progress.

Works in Levels 01 and 10 of Q3 are ongoing. Levels 06, 07, 08 and 09 of Tower Q3 are in operation.

The steel bridges connecting the Towers Q1 and Q2 are currently being finished with raised flooring. The steel bridges connecting the Towers Q2 & Q3 and Q3 & Q4 are currently being covered with aluminium composite cladding material.

Waterproofing and granite tiling works in zone 3 are in progress. Landscaping works continuing in front of Q2 Level 00. The planters of the piazza at Level 00 are being filled with graded sub-base. Advanced works in front of Q3 Level 00 are in progress.

Take a look at our January 2022 Update Video here.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email