Vertical construction works at Level 00 are now complete. The slab over Level 00 (beneath Tower Q1 and Tower Q4) is ready. From this point forward, proprietary void formers are going to be inserted within the thickness of the slab to reduce the its self-weight whilst enhancing the strength of the concrete. Work on the remaining slab over Level 00, (beneath Towers Q2 and Q3) is presently ongoing. Preparation works for the installation of another three construction hoists, (together with the one installed last month) are also ongoing. Vertical construction works have also commenced at Level 01 in Tower Q1 area.