Construction Update – July 2021

The roofing works on Towers Q1 are now complete. Roofing works on Tower Q4 are ongoing. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are ongoing.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of VRF units at roof level of Tower Q3 is in progress. The installation of rainwater & sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 are also in progress. Finishing works in the reception area of Tower Q3 Level 01 are in progress.  Installation of internal staircase railings in Tower Q3 are ongoing. Tower Q3 lift lobby tiling works are ongoing. The closure of the holes of the tower crane in Tower Q3 are in progress.

The floor-to-ceiling and curtain-wall façade is being installed in all the lower floors of Towers Q1, Q2 and Q4 respectively. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q1 respectively, and have commenced in Tower Q2. The sides and underside of these balconies are also being covered with aluminium composite cladding material.

Waterproofing works at Level 00 and Level 01 (Piazza) are in progress while granite tiling works at Level 00 and Level 01 are also in progress. Works on planters are ongoing.

The steel bridges connecting Towers Q1 and Q2 at level 2 have started to be covered with aluminium composite cladding material.

Site offices have now been removed from the Piazza.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email