Construction Update – June 2021

The roofing works on Tower Q2 are now complete. The roofing works on Tower Q4 are in progress. Construction works of Tower Q3 are now complete. Vertical construction works in Tower Q4 on Level 20 are in progress.

The installation of the mechanical and electrical services are in progress at all Basement Levels including the tower cores. Installation of VRF units at roof level of Tower Q3 are ongoing. The installation of rainwater & sewer systems as well as plastering works of all tower cores at all basement levels and in Tower Q3 are also in progress. Finishing works in the reception area of Tower Q3 Level 01 are in progress.  Installation of internal staircase railings in Tower Q3 are ongoing. Tower Q3 lift lobby tiling works are ongoing. Final fire fighting lift installation in Tower Q3 is complete. The closure of the holes of the tower crane besides Tower Q3 have commenced.

The floor-to-ceiling and curtain-wall façade is being installed in all of the lower floors of Towers Q1, Q2 and Q4 respectively. Fixing of the stainless steel railing in the maintenance balconies are ongoing in Towers Q3 & Q1, and have commenced in Tower Q2. The sides and underside of these balconies are also being covered with aluminium composite cladding material.

Waterproofing works at Level 00 and Level 01 (Piazza) are in progress while granite tiling works at Level 00 and Level 01 are also in progress. Works on planters have been commenced.

The steel bridges connecting Towers Q1 and Q2 at level 2 have started to be covered with aluminium composite cladding material.

The transformers of the substation have been replaced by more improved ones.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.