Construction Update – June 2022

Piazza Level 00 has now opened to the public, with three outlets now operational.

The floor-to-ceiling and curtain-wall fa├žade in all the lower floors of Tower Q4 is in progress.

Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 & Q4 with liner and railing works. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The steel bridges connecting the Towers Q1 & Q2 are currently being installed with raised flooring. The aluminium composite cladding material works are ongoing.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the cores of Tower Q2.

Level 10 of Q3 has been handed over. Level 01, 02, 06, 07, 08 and 09 of Tower Q3 are in operation.

The car parking system has been put in operation. Level -1 & -2 of the parking is in operation.

Piazza works are completed in Levels 00 and 01 subject to minor snags to be carried out during the months of July & August.

Landscaping works have started on Level 01.

Take a look at our June 2022 Update Video here.