Construction Update – March 2020

The concrete slab over Level 07 of Tower Q4 is complete and vertical construction works on Level 08 are ongoing. Vertical construction works at Level 06 of Tower Q1 and Tower Q2 are complete, and works are ongoing on the concrete slabs over Level 06 in both towers. The vertical construction and roof over Level 05 of Tower Q3 are complete and preparation works for the concrete slab have started.

The installation of the mechanical and electrical services are continuing at all Basement Levels including the tower cores. The installation of rainwater and sewer systems and plastering works of the tower cores at basement levels is also in progress