Construction Update – March 2022

The roofing works on Tower Q4 are now finished. Installation of VRF units at roof level of Tower Q3 has now been fully completed. Fixing of stainless-steel railing in Tower Q2 roof is in progress.

The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress.

Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1 & Q2. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the cores of Tower Q2.

Works in Levels 01 and 10 of Tower Q3 are ongoing. Level 06, 07, 08 and 09 of Tower Q3 are in operation.

The steel bridges connecting Towers Q1 & Q2 are currently being installed with raised flooring. The steel bridges connecting the Towers Q2 to Q3 and Q3 to Q4 are being covered with aluminium composite cladding material.

Waterproofing and granite tiling works in zone 3 are completed. Landscaping works in front of Q2 Level 00 is now completed. All planters on Level 00 have started to get landscaped & planted.  

Flag poles in the main piazza access have been commissioned.

Take a look at our March 2022 Update Video here.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email