Construction Update – May 2021

Roofing works on Towers Q1 and Q2 are ongoing. Construction works of Tower Q3 are complete. The last concrete slab in Tower Q4 Level 19 is complete and vertical construction works on Level 20 are ongoing. Thus, the floor slabs of all 4 towers are now complete.

The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. Installation of VRF units at roof level of Tower Q3 is in progress. The installation of rainwater and sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 is also in progress. Staircase granite works are complete in Tower Q3 and at all basement levels. Installation of internal staircase railings in Tower Q3 have commenced. Finishing works in the reception area of Tower Q3 Level 01 are in progress.

The floor-to-ceiling and curtain-wall façade is being installed in all the lower floors of the towers Q1, Q2 and Q4 whilst glazed façade installation in Tower Q3 is complete from Level 02 up to Level 16. Fixing of stainless steel railing in the maintenance balconies have started in Towers Q3 and Q1. The sides and underside of these balconies are also being covered with aluminium composite cladding material.

Waterproofing works at Level 00 and Level 01 (Piazza) are in progress while granite tiling works at Level 00 and Level 01 are in progress.

The nine steel bridges connecting the four towers at various levels have all been installed.

Interested in learning more about office space relocation opportunities to The Quad Central? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email