Construction Update – November 2019

During November construction works at The Quad progressed smoothly. The slabs over Level 03 of Tower Q1 and Level 02 of Tower Q3 are in progress and now nearing completion. Vertical construction works on Level 03 of Tower Q2 and Level 04 of Tower Q4 L04 are in progress and also nearing completion. The installation of the mechanical and electrical services is ongoing at Basement Levels. Preparatory works for the installation of rainwater and sewer systems have also continued.