Construction Update – October 2018

The Quad Business Towers – Construction update October 2018

Construction and roofing works at Basement Level B05 together with the circulation ramps connecting Basement Level 05 to Basement Level 04 have been completed during the month of October. Construction works in relation to the vertical walls and columns in all areas of Basement Level 04 are now progress whilst roofing works over Basement Level B04 beneath Towers Q4 and Q2 are now also complete. Vertical construction on the sections below Tower Q1 and Tower Q3, at Basement Level B04 is also in progress.

The 40,000 litre fibre tank has also been lowered into place in the grey water treatment plant area.