Construction Update – November 2020

Construction works progressed on schedule during November. The concrete slab over Level 13 of Tower Q1 is complete and works have commenced on the vertical construction at Level 14. Works on the concrete slab over Level 11 of Tower Q2 are complete and vertical construction works at Level 12 are in progress. The concrete slab over Level 15 of Tower Q3 is complete with vertical construction works at Level 16 in progress. The vertical construction and concrete slab over Level 15 in Tower Q4 is complete.

Mechanical and electrical service installations are continuing at all Basement Levels including the tower cores. Marble and plastering works of all tower cores at basement levels and in Tower Q3 are in progress. The installation of rainwater and sewer systems is in progress and the floor-to-ceiling and curtain-wall façade is continuing to be installed in all the lower floors of the towers.

The installation of two steel bridges linking Tower Q2 to Tower Q3 and the first of the two steel bridge linking Tower Q3 to Tower Q4 is now complete. The next two bridges are presently being manufactured.

Interested in learning more about office space relocation opportunities to The Quad Business Towers? Reach out to one of our representatives here.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
Share on print
Print
Share on email
Email