Roofing works on Towers Q4 are ongoing. Installation of VRF units at roof level of Tower Q3 is in progress. Fixing of stainless-steel railing in Tower Q2 roof have commenced.
The Q2 Tower Crane has been disassembled and the process to enclose the tower crane voids have commenced.
The floor-to-ceiling and curtain-wall façade in all of the lower floors of Towers Q1, Q2 and Q4 is in progress. Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q1, Q2 and Q3. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.
The installation of the mechanical and electrical services is ongoing at all Basement Levels including the tower cores. The installation of rainwater and sewer systems and plastering works of the tower cores at all basement levels and in Tower Q3 is also in progress.
Finishing works in the reception area of Tower Q3 Level 01 are now completed. Levels 06, 07, 08 and 09 of Tower Q3 have been handed over to our first tenants and they are now in operation.
The steel bridges connecting Towers Q1 and Q2 are currently being covered with aluminium composite cladding material. The steel bridges connecting the Towers Q2 to Q3 and Q3 to Q4 are set to be covered with aluminium composite cladding material.
Zone 1 piazza has been completely tiled. Waterproofing and granite tiling works in zone 2 are in progress, and in Zone 3 have commenced. Works on planters are ongoing.
The side boundary blocks facing Triq il-Merghat have been partially removed.