Construction Update - September 2018

Construction Update – September 2018

The Quad Business Towers – Construction update September 2018

Excavation and foundation works beneath the temporary ramp have been completed during the month of September. Construction works relating to the roofing over of the section beneath Tower Q4 at Basement Level B05 is in progress whilst vertical construction works at the sections beneath Tower Q2 and Tower Q3 at Basement Level B04 are now nearing completion. Roofing over of Basement Level B05 beneath Tower Q3 is now complete. Construction works on the two circulation ramps connecting Level B05 to Level B04 have also started. Final preparations are underway in the grey water treatment plant area and the storage tank will shortly be lowered into place.

Find out all development progress details held in October 2018.