The floor-to-ceiling and curtain-wall façade in all of the lower floors of Tower Q4 is in progress.
Fixing of stainless-steel railing in the maintenance balconies are ongoing in Towers Q3 and Q4 with liner & railing works. The sides and underside of these balconies are also being covered with aluminium composite white cladding material.
The works on the steel bridges connecting the towers are ongoing. The aluminium composite cladding material works, the raised flooring and the railing of metal mass is ongoing.
The installation of the mechanical and electrical services is ongoing at all Basement Levels including the cores of Tower Q2.
Levels 01, 02, 05, 06, 07, 08, 09 and 10 of Tower Q3 are in operation.
Works in Levels 03 and 16 of Tower Q3 have commenced.
The fit-out works in Level 01 (Reception and Offices) of Tower Q2 are ongoing.
Carpark Levels -1 and -2 is in operation.
Piazza works are completed in L00 and L01 subject to minor works to be carried out.
Landscaping works are ongoing on Level 01 behind Tower Q4.